Basement Reno Day 5 & 6 & 7

Day 5: new walls for the bathroom

Day5: new walls for the utility room

I’ve clumped the recent days together. A holiday and a family visit took the concentration off the basement for a couple of days.

New purchases: Maax Yarrow shower kit $400 (just polystyrene, not acrylic because of the price difference), Watergenie mascerating toilet, pump and tank ($1000), Diplex bathroom heater ($200).

new walls going up in the future play room - Ah the basement is nice and cool in the summer!

Day 6: adding sound insulation to the bedroom / bandroom walls

Day 6: adding new ductwork to bring some heat into the bedroom :)

Day 7: Adding drywall on top of sound insulation in the bedroom.

Day 7: Adding some plumbing in the bathroom

Day 7: where the new shower will be.

Share and Enjoy:
  • Digg
  • Sphinn
  • del.icio.us
  • Facebook
  • Mixx
  • Google Bookmarks

Posted in reno.

0 Responses

Stay in touch with the conversation, subscribe to the RSS feed for comments on this post.

Some HTML is OK

(required)

(required, but never shared)

or, reply to this post via trackback.