Building the base for the shower p-trap

bathroom behind the scenes

Insulation bedroom outside wall (inside utility room)

moving more air ducts between joists for more headspace

bringing power to the gym

Day 9: adding the new waste water Y-connector from the bathroom to the main pipe

Day 9: Bathroom Insulation around the plumbing

Day 9: Bathroom power

Day 10: Building boxes for the waste pipe in the bathroom

Day 10: closing the bathroom walls

Day 10: Bedroom: Building a box around the ductwork

Day 10: Drywall ceiling around the corner window
2 Responses
Stay in touch with the conversation, subscribe to the RSS feed for comments on this post.
how high did you raise the shower pan off the ground for the pump system?
About 6 inches. That should be enough space for a p-trap underneath the pan (if required, depending on your plumbing setup).